       Active Capital Improvement Projects
       State Road 46                    100% Utilities Complete
       County Road 46                   100% Complete
       17-92                            80% Utilities Complete
       Lake Mary Boulevard Reclaimed
       Water Main extension Phase II    70% Complete
       Cloudbranch Utilities Only       100% Complete
       Midway Utilities Phase II        100% Complete
       815 French Avenue
       (Old Police Station)             95% Complete
       Oak Avenue Utilities Only        50% Complete
       17-92 Beautification Utilities Only  50% Complete
       Terwilliger Trail Utilities Only   50% Complete



























       Cameron Heights
       Pictured above, the contractor is preparing to bore under
       State Road 415 to connect the approximate 160 homes to
       one of three main water connections to the subdivision at
       Cameron Heights. This Subdivision is located on Cameron
       Avenue between Celery Avenue and State Road 46.
       Kensington Reserve
       (Brisson East)
       250 new homes going up in Kensington Reserve. This project
       started late 2016.
       Wyndham Preserve
       (Brisson West)
       The west side of Brisson, better known as Wyndham
       Preserve, is on Phase 3 of development. It was designed for
       approximately 300 households.